Customer San Francisco Unified School District, San Francisco, CA Jobsite Chinese Immersion School (SFUSD) San Francisco, CA 94117 Demo & Base Removal 5,200 SF Fine Grade Baserock Form pour flatwork: WWM, 4″ CC – 5,200 SF, (2) pours with pumps Saw-cut and remove designated areas of concrete along with other minor obstructions as required to construct new improvements. Off-haul and dispose of all debris generated from this work. Remove existing paint and paint new Traffic control: 1 day for sub demo, 2 days for Dryco pours LS Asphalt Impressions: Green Surfacing