Project Description
Scope of Work
- Type 3 barricades at yosemite and humboldt intersection, miscellaneous cones & barricades. Flag men for trucks on large off-haul days and/or pave days.
- Install basic erosion control measures to prevent runoff
- Demolish and remove 1,350 SF of existing asphalt assumed to be 4″ thick. Scarify, grade and compact 26,700 SF area in preparation of 2″ asphalt section
- Form edges for new concrete sidewalk and ramp Type B per City of Pacifica detail
- Remove and replace 32 LF of Type A curb & gutter at driveway approach into park
- Furnish and place 160 LF of standard extruded asphalt berm at 1 locations using self-propelled berm machine
- and install 21 EA 3′ long pre-cast concrete wheel stops using pin down method
- Relocate 1 EA sign and existing sign post
- Paint all new pavement markings using standard traffic paint
- Type 3 barricades at yosemite and humboldt intersection, miscellaneous cones & barricades
- Grind and remove 12,250 SF of existing asphalt assumed to be 4″ thick. Off-haul and dispose of debris
- Replace entrance gate with new gate
- Install 4″ perforate pipe that ties-into existing storm drain structure
- Extend new sub drain an additional 50 LF
- Pulverize existing asphalt, base rock and gravel areas included in base bid area and additive area as indicated