Scope of Work

  • Demo & Base Removal 5,200 SF
  • Fine Grade Baserock
  • Form pour flatwork: WWM, 4″ CC – 5,200 SF, (2) pours with pumps
  • Saw-cut and remove designated areas of concrete along with other minor obstructions as required to construct new improvements.
  • Off-haul and dispose of all debris generated from this work.
  • Remove existing paint and paint new
  • Traffic control: 1 day for sub demo, 2 days for Dryco pours
  • LS Asphalt Impressions: Green Surfacing

Project Details

Services

Customer

San Francisco Unified School District, San Francisco, CA

Jobsite

Chinese Immersion School (SFUSD) San Francisco, CA 94117