Project Description
Scope of Work
- Concrete ADA work, parking lot repairs and seal & stripe
- 4” asphalt section 8500 Sf.
- All pumping was done in one day. Rebar took about 3 weeks
Problems Solved
- ADA non-compliant ramps & parking lot paving was failing and old
Challenges
- Restrictions to work hours
- Facility operations during the project lifespan
- Aggressive deadlines
- We postpone the job paving job due to rain one time
- Matching to preexisting hardscape
Testimonial
- We recently moved our Northern California headquarters into a new 14,000 sq ft facility in Pleasanton. DRYCO was responsible for a complete revitalization of the parking lot, including ADA improvements, sealcoat and striping. The crews showed up early in the morning, got right to work, and by the end of the day all of the concrete and sealcoating was finished. They then came back the next day—a Saturday—to do the striping so we could move in Monday without any interruption to our use of the facility. They were very well organized, with lots of guys and equipment, and no mess left behind. As a contractor myself as well as a business owner, I can appreciate the efficiency and quality of a job well done. Very impressed with DRYCO.Mike Neil, CEO, Allcom Electric



Project Details
Services
Customer
Commercial Management Group
Jobsite
7043 Commerce Circle, Pleasanton CA