Project Description
Scope of Work
Site Work
- Approx. 2500 LF of black vinyl chain link fencing, including pedestrian & vehicle gates as required for facility access
- Work also included installation of removable bollards to facilitate pedestrian vs vehicle access depending on needs of the stadium facility
Problems solved
- The new fence line provides pedestrian and vehicle control leading up to the entry/security gates
Challenges
- Restrictions to work hours
- The stadium continued to operate as usual during Dryco’s work. Work was not to be performed on event days
- Aggressive deadlines
- Work was completed in phases between other scheduled Levi’s events and football games
- Weather/environmental obstacles
- Matching to preexisting hardscape
- Physical obstacles
Project Details
Services
- Saw Cutting
- Fence & Iron
- Striping
Crew
- Majority of work was either a 2-man or 4-man fencing crew. Our striping crew provided assistance with painting bollards prior to installation
Customer
Forty Niners Stadium Management Company
Jobsite
Levis Stadium
900 Marie P DeBartolo Way, Santa Clara, CA 95054