Project Description

Scope of Work

Site Work

  • Approx. 2500 LF of black vinyl chain link fencing, including pedestrian & vehicle gates as required for facility access
  • Work also included installation of removable bollards to facilitate pedestrian vs vehicle access depending on needs of the stadium facility

Problems solved

  • The new fence line provides pedestrian and vehicle control leading up to the entry/security gates

Challenges

  • Restrictions to work hours
  • The stadium continued to operate as usual during Dryco’s work. Work was not to be performed on event days
  • Aggressive deadlines
  • Work was completed in phases between other scheduled Levi’s events and football games
  • Weather/environmental obstacles
  • Matching to preexisting hardscape
  • Physical obstacles

Project Details

Services

Crew

  • Majority of work was either a 2-man or 4-man fencing crew. Our striping crew provided assistance with painting bollards prior to installation

Customer

Forty Niners Stadium Management Company

Jobsite

Levis Stadium

900 Marie P DeBartolo Way, Santa Clara, CA 95054