Project Description
Scope of Work
- Remove five trees complete with stump grinding and remove all debris to dump site
- Paint new pavement marking
- Sawcut, demo curbs and paving and removal
- Saw-cut and remove designated areas of concrete slab for new footings
- Excavate landscape and irrigation and off-haul debris
- Over-excavate all locations 24″ to subgrade elevation
- Set double mats of reinforcing steel per plan
- Furnish and install 10 mil vapor barrier
- Set double mats of reinforcing steel bars
- Furnish, place and compact new hot-mix asphalt paving over class II baserock
- Furnish and install new high chain link fence with plastic slats and three double swing gates