Fencing & Concrete Revamp at LBA Realty – San Francisco, CA

Project Description

Scope of Work

  • Demolish and remove existing chain link and panel fencing
  • Off-haul materials from site
  • Furnish and install 178 LF of 7′ tall and 72 LF of 1 O’ tall chain link fencing
  • Includes top and bottom tension wire with razor ribbon and 3-strand barb wire
  • Furnish and install 631 LF of panel fencing to match existing run
  • Posts to be set in concrete footing
  • Replace gate panel with new 10′ high gate with barb wire and razor ribbon.
  • Track system to remain and new wheel rollers to be installed
  • Fabricate and attach bottom of (3) gate leafs at railroad tracks with fold able and lockable panels to eliminate gap
  • Temp fencing for panel replacement

Project Details

Services

Customer

LBA Realty – San Francisco, CA 94111

Jobsite

8511 Blaine St Oakland, CA 94621