Concrete Dock Floor Patching at Mare Island Drydock – Vallejo, CA

Project Description

Scope of Work: Concrete Dock Floor Patching

  • Cut and square up loose, failed areas.
  • Chip and remove any material that appears to be failing to a depth of 2″-3″.
  • Cut and remove rusted rebar.
  • Sand blast and residue adhered to existing concrete as needed.
  • Install dowels into existing concrete. Apply weld-crete bonding agent to existing surface.
  • Install #3 rebar at 18″ OC.
  • Pump and finish high strength 3/8″ concrete with fibers.
  • 4 locations in total.

Project Details

Services

Customer

Mare Island Dry Dock LLC

Jobsite

1180 Nimitz Ave, Vallejo, CA 94592