Project Description
Scope of Work
- 6500 yards of concrete
- Double mat concrete with walls and columns
- Plus pan decking
- 275 unit apartment complex with below grade parking
Challenges
- The ramp going into the job was very extremely steep, so we had to jack the front end of the pump almost 5’ off the ground.