Project Description
Scope of Work
- Required approximately 100,000 SF of seal coat
- Crack fillings and about 15 Gallons of paint all done in four moves
- Replaced 80 broken wheel stops that surrounded the building
Challenges
- Strong winds which made the spraying process difficult
- Falling leaves required constant blowing off of the lot in order to maintain a clean surface
Project Details
Services
- Seal coating
- Striping
- Replaced broken wheel stops
Crew
- Our foreman on site was Pedro Flores and our seal coat labors included Daniel Flores, Diego Martinez and Daniel Zamora
- Striping crew was composed of three men. Our foreman on site was Arturo Aguilar and the striping labors included Humberto Flores and Alfonso Zuniga
Customer
Fremont Bank Fremont, California
Jobsite
25151 Clawiter Rd Hayward, California